Date : 3 February 2019
Operation Performed :UT Inspection of Weld Joints
Nyaung Don – Ywar Ma ( Ø 14”) ြGas Pipeline Ball Valve Installation System
Client :MYANMA OIL & GAS ENTERPRISE
Date : 18 March 2019
Operation Performed : SAN HANG ZHUANG – 2 Vessel
Ultrasonic Testing on Bottom Plates Weld Joints
Client : Ms CHEC COMPANY LIMITED
Date : 31 January 2019
Operation Performed : MT Inspection on Propeller Shaft Cone Areas
Client : MYANMA FIVE STAR LINE- MV YAAN BYAE
Date : : 2 April 2019
Operation Performed : Magnetic Particle Testing on Bilage Water Tank & F.O Tank
Client : MYANMA FIVE STAR LINE MV HAN THAR
Date : 15 August 2019
Operation Performed : Radiography Test for WPS (Groove Welding)
Client : UNITED ELEPHANTS STEEL SOLUTIONS COMPANY LIMITED
Date : 10 June 2019
Operation Performed : Liquid Penetrant Testing on Propeller Blades & Hub
Magnetic Particle Testing on Fly Wheel, Tail Shaft, Intermidiate Shaft, Flange Shaft & Cone Area
Ultrasonic Testing on F.O Tank Top Plate
Client : MYANMA FIVE STAR LINE MV CO CO GYUN
Date : 29 June 2019
Operation Performed : Upgrading ISO MTD Physical Refining (East Dagon)
Client : PAING SOE INTERNATIONAL COMPANY LIMITED
Date :6 AUGUST 2019
Operation Performed : MAGNETIC PARTICLE TEST ON WELD JOINTS OF STEEL CEMENT SILOS
PRECAST FACTORY (MCDC),
Client : MANDALAY CITY DEVELOPMENT COMMITTEE (MCDC)